Services
No |
Project Description |
Company |
Contract No |
1 |
Construction Underground Pipeline of Production Line 10" - 13KM for Kalila Bentu (Ltd.) Pelalawan Riau |
PT. Petroflexx Prima Daya |
1,508-1-R-0402/SO-KOR/III/12 |
2 |
Pemborongan Pekerjaan Timbun Jalan Tanah |
PT. Laras Karya Kahuripan |
SPJJ/153/LKK/VI/11 |
3 |
Mechanical and Piping Construction Works, Gelam Gas Production Facility |
PT. Petroflexx Prima Daya |
1.443-1-P-08420/SO-IMG/III/11 2008-008-0408 |
4 |
Jasa Water Jet HE/AB (Heat Exchanger) Unit 7 |
PT. Indonesia Power |
1041.SPK/061/UBPSLA/2010 |
5 |
Production Line and Seng Gas Plant Phase-1 Project |
PT. Prime Petroservices |
LTR.470/PPS.X-10 |
6 |
Engineering & Jasa Konstruksi Mekanikal Pembangunan Pabrik Pengolahan Emas |
PT. Cibaliung Sumberdaya |
003/K-CSD/X/09 |
7 |
Jasa Konsultasi Pengawasan Pekerjaan Modifikasi Sistem Penyimpanan Pengganti dan Perbaikan Fasilitas Operasi di Terminal Buatan Lirik |
PT. Pertamina EP Region Sumatera |
S09LL0181 B |
8 |
Pipeline Construction From DC Field - Tanjung Mayung |
PT. Prime Petroservices, |
015/PPS-PSP/VIII/09 |
9 |
Piping Construction for CNG Plant |
PT. Odira Energy Persada |
011/SPK-TG/PIPE/OEP/VI/07 |
10 |
Metering Calibration and Certification |
PT. Pelangi Haurgeulis Resources, Mar. '07 |
001/SO/PHR/1/20. 07 |
11 |
Demolition Work of Oil Production Facility |
PT. Jaya Wijaya Raya, Sep. '06 |
JWR 919-3-P1100B/SO-LBI/IX/06 |
12 |
Pipe & Structure Sandblasting and Painting |
PT. Tiga Sinar Utama, Jun. '06 |
016/TSU-PSP/SO-PO/VI/2006 |
13 |
Hydrant Piping Job's |
PT. Branita Sandhini, Feb. '06 |
260031 |
14 |
Dry Cob Conveyor Job's |
PT. Branita Sandhini, Feb. '06 |
260025 |
15 |
Engineering Drawing for Hazardous Area |
PT. Monagro Kimia, Jan. '06 |
260037 |
16 |
Maintenance of Packaging Area |
PT. Monagro Kimia, Dec. '05 |
250956 |
17 |
Civil Work |
PT. Monagro Kimia, Dec. '05 |
250953 |
18 |
Installing Computer Cable Network |
PT. Monagro Kimia, Oct. '05 |
250884 |
19 |
Pump Installation |
PT. Torishima Guna Engineering, Nov. '05 |
974/LK/XI/2005 |
20 |
Sewerage Mechanical & Electrical Work |
PT. Torishima Guna Engineering, Nov. '05 |
960/LK/X/2055 |
21 |
Pump Installation |
PT. Monagro Kimia, Aug. '05 |
250618 |
22 |
Modification of Jumbo Bag Reactor 3-301 |
PT. Monagro Kimia, Jul. '05 |
250606 |
23 |
General Project Maintenance |
PT. Monagro Kimia, Jul. '05 |
250592 |
24 |
Piping Job for LPG Distribution |
PT. Branita Sandhini, Apr. '05 |
07/BS/EX/04/05 |
25 |
Conveyor Job for BC-01 |
PT. Branita Sandhini, Apr. '05 |
04/BS/EX/04/05 |
26 |
Pipe Modification for Tank D |
PT. Monagro Kimia, Jan. '05 |
250051 |
27 |
Overhaul Heat Exchanger & Chiller |
PT. Maruta Bumi Prima, Sep. '04 |
080904/MBP-PP/2004 |
28 |
Road Asphalt Overlay |
PT. Monagro Kimia, Aug. '04 |
240649 |
29 |
Engineering Survey & Soil Investigation |
PT. Maruta Bumi Prima, Mar. '04 |
012/SO/MBP-BBD/03/04 |
30 |
Electronic & Instrument Compressor System |
PT. Maruta Bumi Prima, Sep. '03 |
078/SO/MBP-BBD/09/03 |
31 |
Piping, Electrical & Instrument and Storage Tank |
PT. Monagro Kimia, Jul. '03 |
003/SPK/PP-MK/VII/03 |
32 |
Repair Tanki 71T-10 |
Pertamina UP-IV Cilacap, Jun. '03 |
33075-JPK |
33 |
Services Heat Exchangers |
PT. Maruta Bumi Prima, Sep. '02 |
099/SO/MBP-BBD/09/02 |
34 |
EPC for Gas Processing Plant, Condensate Storage Tank Cap. 20 MTTAC, Pressure Vessel, Instrument & Electrical, Piping Installation. |
PT. Bumi Hasta Mukti, Jul. '02 |
002/BHM/Jasa/VII/2002 |